What is the key difference between how Versatile measures construction work versus visual progress tracking methods?
Answered at 17:00 in Empowering Builders Through AI with Meirav Oren of Versatile · Leaders of B2B Podcast - Interviews on Business Leadership, B2B Sales, B2B Marketing and Revenue Growth
What is the key difference between how Versatile measures construction work versus visual progress tracking methods?
Versatile measures process, not progress. Visual tracking tells you if something was installed or not, but Versatile tells you how long it took to install it, where materials came from, how long it took to get them there, and what took so long to get stuff off the truck. You can understand stripping and installation on formwork at a level of detail that visual aids alone cannot provide. This process-level detail is what enables actionable insights.
Full answer and detailsRead the whole answer, key facts and every other question from this episode
In short
Versatile measures process, not progress.
Meirav Oren, CEO and co-founder at Versatile · Empowering Builders Through AI with Meirav Oren of Versatile · Leaders of B2B Podcast - Interviews on Business Leadership, B2B Sales, B2B Marketing and Revenue Growth · answer at 17:00
Key takeaways
- Versatile measures process, not progress.
Quote to remember
“Don't slow yourself down. If something needs to be done, don't procrastinate. The world will slow you down enough.”
— Meirav Oren
The full answer · about 3 min
Versatile measures process, not progress. Visual tracking tells you if something was installed or not, but Versatile tells you how long it took to install it, where materials came from, how long it took to get them there, and what took so long to get stuff off the truck. You can understand stripping and installation on formwork at a level of detail that visual aids alone cannot provide. This process-level detail is what enables actionable insights.
Key facts
- Versatile raised over 109 million dollars after bootstrapping
- 70 to 80 percent of construction processes can be seen and controlled through a crane
- 90 seconds per lift savings times thousands of lifts (Internal Construction case study)
- 8 minutes per lift slowdown times 512 lifts (customer case showing compounding effect of undiscovered process change)
- First money raised: winning Mass Challenge accelerator competition
People, companies and topics mentioned
More answers from this episode
- 5:23How does Versatile's smart hook device collect data from construction cranes to measure job site processes?
- 6:10Why did Versatile focus specifically on cranes rather than other construction equipment as its data collection point?
- 11:11How much funding has Versatile raised despite starting as a bootstrapped hardware-enabled SaaS company?
- 19:00What is Versatile's approach to AI analysis of construction data rather than making predictive or prescriptive recommendations?
- 20:37What specific process improvements has Versatile's data revealed for construction customers, such as Internal Construction?