What key milestones is Austral Resources targeting at Mount Kelly in the next 12 to 24 months?

Answered at 16:45 in #91 David Newling: Austral Resources · Connecting Industry

— questions searchable right now

What key milestones is Austral Resources targeting at Mount Kelly in the next 12 to 24 months?

At Mount Kelly, Austral is processing the tail of the Ansel mining campaign related to the APA, and has started mining the Lady Annie Cutback and saddle load between Mount Clark and Flying Horse pits. After completing the Lady Annie Cutback, the company will begin mining sulfide material from Lady Annie Pit, which is an initial feedstock for the Rocklands facility. Mount Kelly has enough feedstock for at least the next six to seven years.

David Newling on Connecting IndustryAll answers from this podcast →
Full answer and detailsRead the whole answer, key facts and every other question from this episode

In short

At Mount Kelly, Austral is processing the tail of the Ansel mining campaign related to the APA, and has started mining the Lady Annie Cutback and saddle load between Mount Clark and Flying Horse pits.

David Newling, Non-Executive Chair at Austral Resources · #91 David Newling: Austral Resources · Connecting Industry · answer at 16:45

Key takeaways

  • At Mount Kelly, Austral is processing the tail of the Ansel mining campaign related to the APA, and has started mining the Lady Annie Cutback and saddle load between Mount Clark and Flying Horse pits.

Quote to remember

“We are the only company in Australia that can process both copper oxides and copper sulfides. That is a unique proposition for us.”

— David Newling

The full answer · about 1 min

At Mount Kelly, Austral is processing the tail of the Ansel mining campaign related to the APA, and has started mining the Lady Annie Cutback and saddle load between Mount Clark and Flying Horse pits. After completing the Lady Annie Cutback, the company will begin mining sulfide material from Lady Annie Pit, which is an initial feedstock for the Rocklands facility. Mount Kelly has enough feedstock for at least the next six to seven years.

Key facts

  • Replacement value of Austral Resources combined assets is over one billion dollars
  • Distance between Austral Resources' two processing facilities is approximately 250 kilometers
  • Rocklands facility expected production target: 26,000 tons of copper metal units per year
  • Snow Queen exploration result: 7.5% copper grade
  • Mount Kelly facility has sufficient feedstock for at least six to seven years

People, companies and topics mentioned

Austral ResourcesSpringwood GroupMount KellyRocklands facilityCloncurry regionMount IsaLady Annie PitErnest Henry