When is Austral Resources planning to commission the Rocklands facility and what production target does it expect?

Answered at 17:30 in #91 David Newling: Austral Resources · Connecting Industry

— questions searchable right now

When is Austral Resources planning to commission the Rocklands facility and what production target does it expect?

Austral Resources is targeting early commissioning of the Rocklands facility in the first half of 2027, with the facility's official start date—referred to as 'the big green button'—on July 27. Once operational, Rocklands is expected to produce approximately 26,000 tons of copper metal units per year.

David Newling on Connecting IndustryAll answers from this podcast →
Full answer and detailsRead the whole answer, key facts and every other question from this episode

In short

Austral Resources is targeting early commissioning of the Rocklands facility in the first half of 2027, with the facility's official start date—referred to as 'the big green button'—on July 27.

David Newling, Non-Executive Chair at Austral Resources · #91 David Newling: Austral Resources · Connecting Industry · answer at 17:30

Key takeaways

  • Austral Resources is targeting early commissioning of the Rocklands facility in the first half of 2027, with the facility's official start date—referred to as 'the big green button'—on July 27.

Quote to remember

“We are the only company in Australia that can process both copper oxides and copper sulfides. That is a unique proposition for us.”

— David Newling

The full answer · about 1 min

Austral Resources is targeting early commissioning of the Rocklands facility in the first half of 2027, with the facility's official start date—referred to as 'the big green button'—on July 27. Once operational, Rocklands is expected to produce approximately 26,000 tons of copper metal units per year.

Key facts

  • Replacement value of Austral Resources combined assets is over one billion dollars
  • Distance between Austral Resources' two processing facilities is approximately 250 kilometers
  • Rocklands facility expected production target: 26,000 tons of copper metal units per year
  • Snow Queen exploration result: 7.5% copper grade
  • Mount Kelly facility has sufficient feedstock for at least six to seven years

People, companies and topics mentioned

Austral ResourcesSpringwood GroupMount KellyRocklands facilityCloncurry regionMount IsaLady Annie PitErnest Henry

More answers from this episode

 ·  All answers from Connecting Industry →
—
—
0:00
0:00