What is the construction timeline and phasing strategy for a 16-story hospital replacement tower?

Answered at 15:55 in Joe Lewandowski, McCarthy PM on BJC Campus Renewal Phase 3 · Forum Focus

— questions searchable right now

What is the construction timeline and phasing strategy for a 16-story hospital replacement tower?

Construction starts in November 2021, with the first patient expected in the tower in summer of 2025, spanning approximately three and a half years. The cast-in-place concrete frame will continue until the third quarter of 2023. As the structure rises, the building skin and enclosure will be constructed from the lower floors upward. Interior fit-out begins once the building becomes enclosed. Construction completion is targeted for the end of 2024.

Joe Lewandowski on Forum FocusAll answers from this podcast →
Full answer and detailsRead the whole answer, key facts and every other question from this episode

In short

Construction starts in November 2021, with the first patient expected in the tower in summer of 2025, spanning approximately three and a half years.

Joe Lewandowski · Joe Lewandowski, McCarthy PM on BJC Campus Renewal Phase 3 · Forum Focus · answer at 15:55

Key takeaways

  • Construction starts in November 2021, with the first patient expected in the tower in summer of 2025, spanning approximately three and a half years.

The full answer · about 1 min

Construction starts in November 2021, with the first patient expected in the tower in summer of 2025, spanning approximately three and a half years. The cast-in-place concrete frame will continue until the third quarter of 2023. As the structure rises, the building skin and enclosure will be constructed from the lower floors upward. Interior fit-out begins once the building becomes enclosed. Construction completion is targeted for the end of 2024.

More answers from this episode