How did the COVID-19 pandemic impact the timeline of a major healthcare campus construction project?

Answered at 5:05 in Joe Lewandowski, McCarthy PM on BJC Campus Renewal Phase 3 · Forum Focus

— questions searchable right now

How did the COVID-19 pandemic impact the timeline of a major healthcare campus construction project?

McCarthy was brought onto the project in December 2019 for design and pre-construction services. The pandemic caused BJC leadership to pause the project for evaluation, resulting in approximately a nine-month delay. The project was originally scheduled to start in spring 2021 but was rescheduled to begin in November 2021. During the pause, the team remained together and found innovative ways to continue collaborating and communicating to keep the design process moving forward.

Joe Lewandowski on Forum FocusAll answers from this podcast →
Full answer and detailsRead the whole answer, key facts and every other question from this episode

In short

McCarthy was brought onto the project in December 2019 for design and pre-construction services.

Joe Lewandowski · Joe Lewandowski, McCarthy PM on BJC Campus Renewal Phase 3 · Forum Focus · answer at 5:05

Key takeaways

  • McCarthy was brought onto the project in December 2019 for design and pre-construction services.

The full answer · about 2 min

McCarthy was brought onto the project in December 2019 for design and pre-construction services. The pandemic caused BJC leadership to pause the project for evaluation, resulting in approximately a nine-month delay. The project was originally scheduled to start in spring 2021 but was rescheduled to begin in November 2021. During the pause, the team remained together and found innovative ways to continue collaborating and communicating to keep the design process moving forward.