Did insurers blacklist solar projects in Texas following major hail losses?
Answered at 12:50 in Resilience is Expensive, Except in Retrospect - Michael Perron (FM) · Raptor Report
Did insurers blacklist solar projects in Texas following major hail losses?
One major renewable energy insurer stated they would not insure hail in Texas until the industry figured out resilience, which scared many stakeholders. However, that insurer had paid a $75 million sole-loss in 2019 and taken pieces of other big losses. That same company is now back in the business of insuring risk in Texas, though not fully confident everyone is doing it correctly, but closer than before.
Full answer and detailsRead the whole answer, key facts and every other question from this episode
In short
One major renewable energy insurer stated they would not insure hail in Texas until the industry figured out resilience, which scared many stakeholders.
Michael Perron, Renewable Energy Market Lead at FM Global · Resilience is Expensive, Except in Retrospect - Michael Perron (FM) · Raptor Report · answer at 12:50
Key takeaways
- One major renewable energy insurer stated they would not insure hail in Texas until the industry figured out resilience, which scared many stakeholders.
Quote to remember
“Resilience is expensive, except in retrospect.”
— Michael Perron
The full answer · about 2 min
One major renewable energy insurer stated they would not insure hail in Texas until the industry figured out resilience, which scared many stakeholders. However, that insurer had paid a $75 million sole-loss in 2019 and taken pieces of other big losses. That same company is now back in the business of insuring risk in Texas, though not fully confident everyone is doing it correctly, but closer than before.
Key facts
- 2019: $75 million hail loss that insurers were not expecting
- 2022: Three major hail events in Texas ranging from $30 to $50 million each
- KWH Analytics data shows hail losses represent 73% of what insurers pay out
- 1-in-50-year hail basis used in FM Global's kinetic energy calculations
- FM Global: 6,000 total employees with 2,000 engineers on staff
People, companies and topics mentioned
More answers from this episode
- 3:00Why did FM Global and VDE separately verify Colin Sillerud's research on 75-degree panel stow angles at PVRW 2024?
- 10:00What was the financial impact of major hail losses on solar insurers between 2019 and 2022?
- 15:20What percentage of solar insurance losses does KWH Analytics data attribute to hail damage?
- 23:00How does FM Global's physics-based approach calculate panel resilience against hail in specific counties?
- 28:00What role do hail sensors play in solar project resilience monitoring and loss prevention?