Listenly

How much value has National Highways processed through project bank accounts and what payment speed have they achieved?

Answered at 25:40 in 197: Rudi Klein on payment reform · Re:Construction

— questions searchable right now

How much value has National Highways processed through project bank accounts and what payment speed have they achieved?

National Highways has put through approximately 20 to 25 billion pounds worth of work through project bank accounts. They pay all their contractors, including subcontractors, within 18 days, demonstrating that project bank accounts enable faster payment cycles and provide protection by limiting exposure to at most the value of work in the current payment cycle.

Rudi Klein on Re:ConstructionAll answers from this podcast →
Full answer and detailsRead the whole answer, key facts and every other question from this episode

In short

National Highways has put through approximately 20 to 25 billion pounds worth of work through project bank accounts.

Rudi Klein, Barrister and Director at Klein Legal · 197: Rudi Klein on payment reform · Re:Construction · answer at 25:40

Key takeaways

  • National Highways has put through approximately 20 to 25 billion pounds worth of work through project bank accounts.

Quote to remember

“You can't collaborate with anybody who's actually not paying you. So any reform or transformation of the industry must require this whole subject of payment to be addressed.”

— Rudi Klein

The full answer · about 1 min

National Highways has put through approximately 20 to 25 billion pounds worth of work through project bank accounts. They pay all their contractors, including subcontractors, within 18 days, demonstrating that project bank accounts enable faster payment cycles and provide protection by limiting exposure to at most the value of work in the current payment cycle.

Key facts

  • National Highways processes 20 to 25 billion pounds worth of work through project bank accounts
  • National Highways pays contractors within 18 days via project bank accounts
  • Government consultation on payment reform launched July 2024, closed October 2024
  • Scotland and Wales mandate project bank accounts for projects valued at £2 million and above
  • Payment periods proposed capped at 60 days maximum

People, companies and topics mentioned

Klein LegalSpecialist Engineering Contractors GroupProject bank accountMinistry of JusticeISGCarillionNational HighwaysScotland payment reform legislation

More answers from this episode

 ·  All answers from Re:Construction →
—
—
0:00
0:00