How long did workers spend on road patching work on the Eastlink project?
Answered at 15:00 in Episode 7.9: Ray 'Rowdy' Smith (Pt. 1) · Creatures of the Industry
How long did workers spend on road patching work on the Eastlink project?
Ray Smith and his mate Ed patched approximately 30 kilometres of Eastlink over a period of a few years working with Clifton. They were subbed out to contractors like Hollands or Fiesa and given a ute with their gear to work their way through the patching sections.
Full answer and detailsRead the whole answer, key facts and every other question from this episode
In short
Ray Smith and his mate Ed patched approximately 30 kilometres of Eastlink over a period of a few years working with Clifton.
Ray Smith · Episode 7.9: Ray 'Rowdy' Smith (Pt. 1) · Creatures of the Industry · answer at 15:00
Key takeaways
- Ray Smith and his mate Ed patched approximately 30 kilometres of Eastlink over a period of a few years working with Clifton.
The full answer · about 2 min
Ray Smith and his mate Ed patched approximately 30 kilometres of Eastlink over a period of a few years working with Clifton. They were subbed out to contractors like Hollands or Fiesa and given a ute with their gear to work their way through the patching sections.
More answers from this episode
- 2:00How did a music industry professional transition into construction labouring in 2004?
- 5:00What contamination issues were encountered on the Coot Island redevelopment project?
- 10:00What safety incident occurred during night shift work on an active railway bridge construction?
- 12:30What unusual item was discovered embedded in a concrete deck pour on the Long Walk bridge?
- 15:45What injury recording practices did contractors try to enforce on the Eastlink project?
- 16:40What union agreements governed work conditions on the Eastlink project?
- 20:00What safety concern arose during railway station upgrade work at Nunna Wadding?
- 24:00How did different contractor management styles affect worker conditions on the Eastlink project?
- 25:55What workplace facilities issue did a union delegate address on the Heatherhill Road overpass section of Eastlink?
- 30:30What was the significance of school construction projects during the global financial crisis period?