How does Iron Mountain's decommissioning workflow differ between CPU server deployments and GPU-dense AI infrastructure?
Answered at 10:30 in The Circular Supply Chain for AI Hardware · The Dynamo Show: a Dynamo Ventures Podcast
How does Iron Mountain's decommissioning workflow differ between CPU server deployments and GPU-dense AI infrastructure?
At a high level, the workflow does not differ significantly. Iron Mountain has decades of experience producing reusable CPU components and systems for secondary markets. For GPU equipment, while the company does not yet have decades of experience, it is already seeing tremendous appetite for used GPU and AI equipment in secondary use. Tom Delahunty notes that GPU equipment is likely to follow the same longevity curve as CPU did, with increasing usable life extension observed over recent years.
Full answer and detailsRead the whole answer, key facts and every other question from this episode
In short
At a high level, the workflow does not differ significantly.
Tom Delahunty, VP of Operations for Asset Lifecycle Management at Iron Mountain · The Circular Supply Chain for AI Hardware · The Dynamo Show: a Dynamo Ventures Podcast · answer at 10:30
Key takeaways
- At a high level, the workflow does not differ significantly.
Quote to remember
“I see it as a supply chain opportunity. I would look, my lens says those assets have a future in life.”
— Tom Delahunty
The full answer · about 1 min
At a high level, the workflow does not differ significantly. Iron Mountain has decades of experience producing reusable CPU components and systems for secondary markets. For GPU equipment, while the company does not yet have decades of experience, it is already seeing tremendous appetite for used GPU and AI equipment in secondary use. Tom Delahunty notes that GPU equipment is likely to follow the same longevity curve as CPU did, with increasing usable life extension observed over recent years.
Key facts
- Iron Mountain serves almost 225,000 organizations with data storage and records management
- Q4 2025: approximately 70% year-over-year growth in asset lifecycle management
- Q2 2025: plus 88% year-over-year growth and plus 82% organic growth
- One international customer's decommissioning project spans five months and touches seven countries
- AI infrastructure racks scale from 12-15 kilowatts up to 100 kilowatts and beyond
People, companies and topics mentioned
More answers from this episode
- 4:00What growth metrics did Iron Mountain's asset lifecycle division achieve in Q2 and Q4 2025?
- 6:02What is the decommissioning process for data center equipment at Iron Mountain, from de-racking through disposition?
- 12:08What operational challenges arise from liquid cooling in AI infrastructure during the decommissioning process?
- 19:48What drives increasing customer acceptance of used and refurbished GPU and AI equipment in secondary markets?
- 23:48What infrastructure and R&D investments does Iron Mountain believe the ITAD industry needs to handle future AI hardware volumes?