What growth metrics did Iron Mountain's asset lifecycle division achieve in Q2 and Q4 2025?
Answered at 4:00 in The Circular Supply Chain for AI Hardware · The Dynamo Show: a Dynamo Ventures Podcast
What growth metrics did Iron Mountain's asset lifecycle division achieve in Q2 and Q4 2025?
Iron Mountain recorded approximately 70% year-over-year growth in Q4 2025. In Q2, the asset lifecycle division achieved plus 88% year-over-year growth and plus 82% organic growth, driven by tremendous volume of assets coming to end-of-use in the data center and AI space as customers require secure, scalable solutions for large-volume asset decommissioning.
Full answer and detailsRead the whole answer, key facts and every other question from this episode
In short
Iron Mountain recorded approximately 70% year-over-year growth in Q4 2025.
Tom Delahunty, VP of Operations for Asset Lifecycle Management at Iron Mountain · The Circular Supply Chain for AI Hardware · The Dynamo Show: a Dynamo Ventures Podcast · answer at 4:00
Key takeaways
- Iron Mountain recorded approximately 70% year-over-year growth in Q4 2025.
Quote to remember
“I see it as a supply chain opportunity. I would look, my lens says those assets have a future in life.”
— Tom Delahunty
The full answer · about 2 min
Iron Mountain recorded approximately 70% year-over-year growth in Q4 2025. In Q2, the asset lifecycle division achieved plus 88% year-over-year growth and plus 82% organic growth, driven by tremendous volume of assets coming to end-of-use in the data center and AI space as customers require secure, scalable solutions for large-volume asset decommissioning.
Key facts
- Iron Mountain serves almost 225,000 organizations with data storage and records management
- Q4 2025: approximately 70% year-over-year growth in asset lifecycle management
- Q2 2025: plus 88% year-over-year growth and plus 82% organic growth
- One international customer's decommissioning project spans five months and touches seven countries
- AI infrastructure racks scale from 12-15 kilowatts up to 100 kilowatts and beyond
People, companies and topics mentioned
More answers from this episode
- 4:00What growth metrics did Iron Mountain's asset lifecycle division achieve in Q2 and Q4 2025?
- 6:02What is the decommissioning process for data center equipment at Iron Mountain, from de-racking through disposition?
- 10:30How does Iron Mountain's decommissioning workflow differ between CPU server deployments and GPU-dense AI infrastructure?
- 12:08What operational challenges arise from liquid cooling in AI infrastructure during the decommissioning process?
- 19:48What drives increasing customer acceptance of used and refurbished GPU and AI equipment in secondary markets?
- 23:48What infrastructure and R&D investments does Iron Mountain believe the ITAD industry needs to handle future AI hardware volumes?